Our New House - Index
This page is a journal of the building of our new house.
Click on one of the pictures below to see more pictures and details
|
Page 1 Starts with the block after the old house had been demolished, up until the bricks have been laid up to floor level. 3rd March - 20th June 2000 |
|
|
Page 2 Starts with the base brickwork finished, up until the frame for the ground floor has been erected. 30th June - 4th July 2000 |
|
|
Page 3 Starts with the frame for the first floor being erected, up until the frame and roof being completed. 27th July - 31st July 2000 |
|
|
Page 4 Starts with the sarking and plumbing completed, up until the brickwork for the lower third of the house has been started. 3rd August - 14th August 2000 |
|
|
Page 5 Starts with the brickwork for the lower third being almost completed, up until the brickwork for the upper part of the hose being started. 16th August - 21st August 2000 |
|
|
Page 6 Shows the progress of the brickwork, to the point of it being almost complete. 28th August - 31st August 2000 |
|
|
Page 7 Shows the finsihing off of the brickwork, the fitting of the floors, and heater ducts. 20th September - 21st September 2000 |
|
|
Page 8 Shows the timber flooring and staircase fully installed 8th October 2000 |
|
|
Page 9 The wiring has been done, the spa, bath and shower bases fitted, the insulation is in, and the slab in the garage has been laid. 11th October - 19th October 2000 |
|
|
Page 10 The plasterers have finally shown up, and have laid most of the plaster on the first floor. 2nd November 2000 |
|
|
Page 11 The plasterers have just about finished. 12th December 2000 |
|
|
Page 12 The painters are in. 10th January 2001 |
|
|
Page 13 The tiling has begun. 25th January 2001 |
|
|
Page 14 Kitchen and Electrical fit out. 2nd February 2001 |
|
|
Page 15 Its complete! Well, practically, anyway! 26th February 2001 |
|
|
What will it look like when its finished? This page shows several pictures and plans from the brochure. |
|
|
Update: After we moved in This page shows several pictures of the house since we have moved in 21st November 2001 |
|
|
Update: After we moved in This page shows several pictures of the house since we have moved in 3rd February 2002 |
|
|
Update: After we moved in This page shows several pictures of the front garden when it is nearly finished 27th June 2003 |